Addition & Improvement Regulations
Permit requirements are based on the property improvement, but all improvements must meet certain standards.
Required Inspections
The following inspections are required prior issuing a certificate of occupancy which is needed before a dwelling can be occupied. Call the Building Services Division at (816) 316-4817 at least 24 hours prior to your desired inspection time.
- Footing inspection after the rebar has been placed and prior to the pouring of concrete.
- Foundation-wall inspection after the rebar has been placed and prior to the pouring of concrete.
- Ground rough plumbing inspection prior to the pouring of the concrete floor or the placement of the sub-floor in the case of a crawl space.
- Sewer connection prior to backfilling the trench.
- Rough-in inspection prior to the placement of insulation or drywall. This inspection will include the inspection of the rough carpentry, rough plumbing, rough electrical, and the rough mechanical systems. In addition, if the electrical service, and/or the gas service is ready for inspection we will clear those to their respective utilities. However, if necessary we will provide separate inspections of these services.
- The final inspection, when project is complete, prior to the owner moving in!